*Service Suspension*

Streetcar Service Suspension Begins September 30, 2024

MILESTONE ALERT: KC Streetcar Prepares for Main Street Extension Tie-in

The KC Streetcar team is reaching a major milestone in its Main Street Extension project by preparing to “tie in” and connect the extension with the downtown route. In order to complete these critical tie-in construction activities, downtown KC Streetcar service will be temporarily suspended for approximately four weeks.

The temporary service suspension began on September 30, 2024, and will last approximately four weeks. All work and scheduling are dependent on weather and other unforeseen circumstances. During this period, the KC Streetcar Constructors will operate 24-hour shifts, including weekend work, to complete the necessary construction.

Additionally, while streetcar service is suspended, the KC Streetcar team will also perform track and route maintenance on the downtown route. This work includes the rehab of track slab and construction of new track drains at 20th Street and Main Street. This work will take place during daytime hours, and not during overnight hours. Some work may happen on a Saturday as well.

This construction activity for the next several weeks represents a key step in extending the KC Streetcar system and bringing enhanced transit access to more of Kansas City. We appreciate the public’s patience as we work to deliver a stronger and more connected KC Streetcar transit system.

RIDE KC BUS SERVICE WILL BE PROVIDED DURING THIS TIME

To ensure transit services continue, a dedicated “Streetcar Link” bus service is deployed on the route, maintaining public transportation coverage along the streetcar route throughout the temporary suspension. While KC Streetcar service is temporarily suspended, we are operating Ride KC buses on the streetcar route. These buses are free to ride, stop at designated streetcar stops, and operate with regular streetcar hours. The service frequency will be 10-15 minutes.

Northbound and Southbound sound riders will utilize the same stop at Union Station. The pick up/drop off location is located north of the Union Station Streetcar Stop and marked with signage.

Passengers boarding at the River Market North stop will board from the sidewalk on the north side and NOT from the streetcar stop. This is also marked with signage.

WHY THE SERVICE SUSPENSION IS NECESSARY

This service suspension is necessary in order to connect the existing downtown streetcar system to the Main Street Extension tracks. Other work taking place during the service shut down include: 

  • Removal of the existing crossover north of Pershing Road.
  • Replacement of expansion joints on the Main Street Viaduct/Bridge.
  • Construction of new track near the Pershing Road crossover.
  • Rail welding to connect the existing line with the new Pershing Crossover.
  • Pouring the final bridge deck on the Main Street viaduct.
  • Adjustments to the Overhead Catenary System (OCS).
  • Installation of real-time arrival signs.
  • Finalization of the new Union Station Northbound platform and shelter.

Stay updated on the exciting Main Street Extension Pershing Tie-in construction activities by visiting this blog (https://www.buildkcstreetcar.com/project-news/main-street-extension-tie-in). Information and photos will be updated Monday-Friday.

TRAFFIC IMPACTS

  • Main Street Southbound between Pershing Road and 20th Street will remain open during construction.
  • Main Street Northbound between Pershing Road and 20th Street closed on September 23 and is expected to reopen once work is complete.
  • 20th Street at Main Street to close September 30 for approximately 2-3 weeks.
  • Sidewalks and pedestrian access will remain open.
  • No parking along Main Street between 20th & Pershing during this time.

STAY CONNECTED WITH TEXT ALERTS

To receive service alerts by text message or email, sign up by texting the word ‘streetcar’ to 816.685.8541.