Construction On Track

Project remains on Schedule, Budget

 

3-Charts_5.1.2015-700x400Streetcar construction remains on schedule and on budget, with all key construction activities at least 70 percent complete.

As of May 1, 2015:

  • 71% of track is fully constructed (15,430 feet complete out of 21,771 total feet)
  • 96% of water and sewer replacements and upgrades are complete
  • 77% of work on the Singleton Yard vehicle maintenance facility is complete
  • More than 100 power poles are installed
  • First streetcar stop is built at 16th and Main

Read more about the recent construction progress in this news release.